Roanne to Digoin partial closure

More
17 Jun 2024 12:30 #139854 by Richard Hyman
Replied by Richard Hyman on topic Roanne to Digoin partial closure
It is now official: VNF have announc 
This attachment is hidden for guests.
Please log in or register to see it.
ed that the canal will re-open this Friday.
The following user(s) said Thank You: Bob Marsland

Please Log in or Create an account to join the conversation.

More
14 Jun 2024 16:37 #139813 by Richard Hyman
Replied by Richard Hyman on topic Roanne to Digoin partial closure
Good news (I hope): VNF announce that the repairs should be finished by the end of the day. It will take about a week to refill the 18 km pound, allowing the locks to re-open at the end of next week.
The following user(s) said Thank You: Bob Marsland

Please Log in or Create an account to join the conversation.

More
31 May 2024 16:24 #139593 by Richard Hyman
Replied by Richard Hyman on topic Roanne to Digoin partial closure
Latest information is that work commenced on Monday 27 May. VNF plan to begin filling the breach with concrete on Monday 3 June. This will need to be done a number of times before they can refill the canal and re-open to traffic.

Please Log in or Create an account to join the conversation.

More
27 May 2024 22:57 #139559 by Richard Hyman
Replied by Richard Hyman on topic Roanne to Digoin partial closure
Still silence from VNF, but a local newspaper report says (probably) end of June
Roannais. Canal Roanne-Digoin : une réouverture espérée d'ici fin juin (leprogres.fr)

Please Log in or Create an account to join the conversation.

More
15 May 2024 12:41 #139428 by Richard Hyman
Replied by Richard Hyman on topic Roanne to Digoin partial closure
Still nothing official from VNF about re-opening, but local rumour suggests late June

Please Log in or Create an account to join the conversation.

More
07 May 2024 19:58 #139372 by Richard Hyman
Replied by Richard Hyman on topic Roanne to Digoin partial closure
Latest from VNF is that the closure will be for at least 3 weeks, probably longer.

Please Log in or Create an account to join the conversation.

More
06 May 2024 13:34 #139359 by Richard Hyman
Roanne to Digoin partial closure was created by Richard Hyman
There has been a major leakage near Iguerande, and the canal is currently closed between locks 1 and 6. The solution will probably be to drain the affected section (between Briennon and Artaix) for emergency repairs. Anyone moored on this long pound risks being left hanging!